Completion Date
July 2025
Status Updated
October, 2024
| SL. No | Name of the work | Progress details | Remarks |
| 01 | Foundation work | 100% completed. | |
| 02 | Super Structure work | 100% Completed | |
| 03 | Brick Work | GF 50%, A1-100%, B1-100%, A2- 100%, B2-100%, A3-100%, B3-100%, A4-100%, B4-100%,A5-100%, B5-100%, A6-100% B6-100%, B7-100%, A7-100% | |
| 04 | Electrical work (Slab Conduit) | 100% Conduit laying done on Slab | |
| 05 | Door frame fitting work | 100% Complete | |
| 06 | Sanitary & plumbing line work | 100% Complete | |
| 07 | In side Plastering work | 100% Complete | |
| 08 | Electrical cable wiring work | 85% Complete | |
| 09 | Wall tiles work | 95% Complete | |
| 10 | Common sanitary & Plumbing line work | 60% Complete | |
| 11 | Outside plastering work | 97% Complete | |
| 12 | Floor tiles/Marble work | 85% Complete | |
| 13 | L.C.C work | ||
| 14 | Grill & Railing work | 85% Complete | |
| 15 | Inside paint & Polishing work | 30% Complete | |
| 16 | Switch -Socket fitting work | ||
| 17 | Outside paint work | ||
| 18 | Door shutter work | ||
| 19 | Aluminum/Glazing work | ||
| 20 | Tiles Pointing work & Marble finishing work | ||
| 21 | Commode – Basin fitting work and C.P fittings work | ||
| 22 | Lift/Generator /Substation /Solar work | ||
| 23 | Boundary wall /Ground floor development work | 15% Complete | |
| 24 | Land escape /Logo work | ||
| 25 | Roof top finishing work | ||
| 26 | Roof top Gardening work | ||
16604