Completion Date
July 2025
Status Updated
October, 2024
| SL. No | Name of the work | Progress details |
| Foundation work | 100% Completed | |
| Super Structure work | 98% completed | |
| Block work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
| Electrical conduit work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
| Door frame fitting work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100% | |
| Sanitary & plumbing line work | A-1=80%,A-2=80%,A-3=80%,A-4=80%,A-5=80%,A-6=80%,A-7=80%,A-8=80%,A-9=80%. | |
| In side Plastering work | A-1=90%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
| Electrical cable wiring work | A-1=100%,A-2=100%,A-3=100%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
| Wall tiles work | A-1=90%,A-2=90%,A-3=90%,A-4=100%,A-5=100%,A-6=100%,A-7=100%,A-8=100%,A-9=100%. | |
| Common sanitary & Plumbing line work | 25% | |
| Outside plastering work | 95% | |
| Floor tiles/Marble work | 95% | |
| L.C.C work | 100% | |
| Grill & Railing work | 90% | |
| Inside paint & Polishing work | 50% | |
| Switch -Socket fitting work | 20% | |
| Outside paint work | 20% | |
| Door shutter work | 80% | |
| Aluminum/Glazing work | 70% | |
| Tiles Pointing work & Marble finishing work | 35% | |
| Commode – Basin fitting work and C.P fittings work | 15% | |
| Lift/Generator /Substation /Solar work | 80% | |
| Boundary wall /Ground floor development work | 80% | |
| Roof top finishing work | 90% | |
| Roof top Gardening work | 80% |