Completion Date
May 2025
Status Updated
October, 2024
| SL. No | Name of the work | Location | Progress details | Remarks |
| 01 | Foundation work | 100% completed. | ||
| 02 | Super Structure work | 97% | ||
| 03 | Block Work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof Top |
85% Complete
97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 95% Complete 90% Complete 00% Complete
|
|
| 04 | Electrical conduiting work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof Top |
95% Complete
95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 97% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete |
|
| 05 | Door frame fitting work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top |
00% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 75% Complete 00% Complete 00% Complete |
|
| 06 | Sanitary & plumbing line work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top |
00% Complete
85% Complete 85% Complete 85% Complete 85% Complete 85% Complete 95% Complete 95% Complete 90% Complete 90% Complete 85% Complete 85% Complete 85% Complete 80% Complete 80% Complete 80% Complete 40% Complete 30% Complete 10% Complete |
|
| 07 | In side Plastering work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top
|
50 % Complete
95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 95% Complete 65% Complete 45% Complete 00% Complete |
|
| 08 | Electrical cable wiring work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top |
00% Complete
20% Complete 20% Complete 20% Complete 20% Complete 20% Complete 80% Complete 80% Complete 80% Complete 80% Complete 80% Complete 20% Complete 30% Complete 30% Complete 30% Complete 30% Complete 00% Complete 00% Complete 00% Complete |
|
| 09 | Wall tiles work | Community Hall
Apartment =A2 Apartment =C2 Apartment =D2 Apartment =A3 Apartment =B3 Apartment =A4 Apartment =B4 Apartment =A5 Apartment =B5 Apartment =A6 Apartment =B6 Apartment =A7 Apartment =B7 Apartment =A8 Apartment =B8 Apartment =A9 Apartment =B9 Roof top |
00% Complete
60% Complete 60% Complete 60% Complete 60% Complete 60% Complete 60% Complete 60% Complete 60% Complete 60% Complete 60% Complete 60% Complete 60% Complete 40% Complete 00% Complete 00% Complete 00% Complete 00% Complete 00% Complete
|
|
| 10 | Common sanitary & Plumbing line work | 0%
|
||
| 11 | Outside plastering work | 35% Complete | ||
| 12 | Floor tiles/Marble work | 30% Complete | ||
| 13 | L.C.C work | |||
| 14 | Grill & Railing work | |||
| 15 | Inside paint & Polishing work | |||
| 16 | Switch -Socket fitting work | |||
| 17 | Outside paint work | |||
| 18 | Door shutter work | |||
| 19 | Aluminum work | |||
| 20 | Tiles Pointing work & Marble finishing work | |||
| 21 | Commode – Basin fitting work and C.P fittings work | |||
| 22 | Lift/Generator /Substation /Solar work | |||
| 23 | Boundary wall /Ground floor development work | |||
| 24 | Roof top finishing work | |||
| 25 | Roof top Gardening work G.F Garden work |