Montage

Bashundhara R/A, Dhaka

Completion Date

March 2025

Status Updated

October, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 95% completed
  Block work A-1=100%, A-2=100%, A-3=100%,           A-4=100%, A-5=100%, A-6=100%,                  A-7=100%
  Electrical conduit work A-1=100%, A-2=100%, A-3=100%,            A-4=100%  A-5=100%, A-6=100%,            A-7=100%
  Door frame fitting work A-1=100%, A-2=100%, A-3=100%,            A-4=100%  A-5=100%, A-6=100%,           A-7=100%
  Sanitary & plumbing line work A-1=40%, A-2=40%, A-3=40%, A-4=40%                   A-5=40%, A-6=40%, A-7=40%
  In side Plastering work A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A-   7=100%
  Electrical cable wiring work 70%
  Wall tiles work 65%
  Common sanitary & Plumbing line work N/A
  Outside plastering work 90%
  Floor tiles/Marble work 70%
  L.C.C work N/A
  Grill & Railing work 65%
  Inside paint & Polishing work N/A
  Switch -Socket fitting work N/A
  Outside paint work N/A
  Door shutter work N/A
  Aluminum/Glazing work N/A
  Tiles Pointing work & Marble finishing work N/A
  Commode – Basin fitting work and C.P fittings work N/A
  Lift/Generator /Substation /Solar work N/A
  Boundary wall /Ground floor development work 45%
  Roof top finishing work 75%
  Roof top Gardening work N/A

 