Completion Date
March 2025
Status Updated
October, 2024
| SL. No | Name of the work | Progress details |
| Foundation work | 100% Completed | |
| Super Structure work | 95% completed | |
| Block work | A-1=100%, A-2=100%, A-3=100%, A-4=100%, A-5=100%, A-6=100%, A-7=100% | |
| Electrical conduit work | A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A-7=100% | |
| Door frame fitting work | A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A-7=100% | |
| Sanitary & plumbing line work | A-1=40%, A-2=40%, A-3=40%, A-4=40% A-5=40%, A-6=40%, A-7=40% | |
| In side Plastering work | A-1=100%, A-2=100%, A-3=100%, A-4=100% A-5=100%, A-6=100%, A- 7=100% | |
| Electrical cable wiring work | 70% | |
| Wall tiles work | 65% | |
| Common sanitary & Plumbing line work | N/A | |
| Outside plastering work | 90% | |
| Floor tiles/Marble work | 70% | |
| L.C.C work | N/A | |
| Grill & Railing work | 65% | |
| Inside paint & Polishing work | N/A | |
| Switch -Socket fitting work | N/A | |
| Outside paint work | N/A | |
| Door shutter work | N/A | |
| Aluminum/Glazing work | N/A | |
| Tiles Pointing work & Marble finishing work | N/A | |
| Commode – Basin fitting work and C.P fittings work | N/A | |
| Lift/Generator /Substation /Solar work | N/A | |
| Boundary wall /Ground floor development work | 45% | |
| Roof top finishing work | 75% | |
| Roof top Gardening work | N/A |