Moonwake

Dhanmondi, Dhaka

Completion Date

December 2024

Status Updated

October, 2024

SL. No Name of the work Progress details
1 Supper structure  100% Completed
2 Ceiling plaster 2nd to 13th floor 100%
3 Block work 2nd to 13th floor 100%
  Wall plaster A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-5, 100%, C-5 100%, C6- 100%. A7- 100%, B7 100%.C7- 90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11- 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%, C13- 100 %.
4 Electrical conducting work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%, C13- 70 %.
5 Door frame fitting work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%, C13- 90 %.
6 Sanitary & plumbing (INTERNAL WIRING) A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-90%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%
8 Electrical cable wiring work A2- 100%, B-2 100 %, C2-100%, A3-100%. B3- 100%, C3-100%, A4- 100%, B4- 100%, C4- 100%, A5-100%, B-100%, C6- 100%. A7- 100%, B7 100%.C7-100%. A8 100%, B8 100% C8 100%. A9 100%, B9 100%, C9 100%. A10 100%, B10 100%, C10 100%, A11 100%, B11 100%, C11 100%, A12 100%, B12-100%, C12 100%, A13 100%, B13 100%, C-13 0%.
9 Wall tiles work A2 100 %, B2 – 0%, C2-100%, A3- 100%, B3-100%, C3-100%, A4-100%, B4- 100% C4-100%, A5-100%, B5 100%, C5 100%. A6-100%, B6-100%, C6-100%, A7-100%, B7- 100 %, C7-100%, A8- 100%, B8-100%, C8-100%, A9 -100%, B9 -100%, C9 100%, A10 100 %, B10-100%, C10-100 %, A11-80%, B11-100%, C-11 80%, A12- 100%, B12- 100%, C12-100%, A13-70%, B13-100%. C13 – NYS
10 Sanitary & Plumbing VERTICAL line work 90%
11 Outside plastering work 100%
12 Floor tiles/Marble work A2-95%, C2-95%, A-3 50%, B3-90%, C3-100%, A4-100%, B4-100%, C4-100%, A5-100%, B5- 100%, C-5, 100%, A6-100%, B6-95% C6-90%, A7-100%, B7-80%, C7- 100%, A8-100%, B8-100%, C8-100%, A9-100%, B9-90%, C9-100%, A10-100%, B10-100%, C10-100%, A11-90%, B11-90%, C11-90% A12-100%, B12-100%, C12- 100%, A13-80%, B13-80%.

 

13 Facing Bricks (Outside) 90% done.
14

 

L.C.C work NYS
15 Grill & Railing work A2-90%, C2-100%, C3-100%, A4-90%, B4-90%, C4-100%, A5-

90%, B5- C-5, 100%, A6-90%, C6-90%, A7-90%, C7- 100%, A8-90%, C8-100%, A9-90%, C9-100%, A10-90%, B10-90%, C10-100%, A11-90%, C11-100% A12-90%, B12-90%, C12- 100%, A13-70%,

16 Inside paint & Polishing work 1ST COAT=A8-70%, B8-70%, C8-70%, A10-70%, B10-70%, C10-70%, A12-70%, B12-70%, C12-70%
17 Switch -Socket fitting work  
18 Outside paint work 20% completed
19 Door shutter work NYS
20 Aluminum/Glazing work 15% completed
20 Tiles Pointing work & Marble finishing work  
21 Commode – Basin fitting work and C.P fittings work  

 

22 Lift/Generator /Substation /Solar work Substation supply done.
23 Boundary wall /Ground floor development work 60% done.
24 Roof top finishing work 20% completed
25 Roof top Gardening work NYS