Completion Date
December 2024
Status Updated
October, 2024
SL. No | Name of the work | Progress details
|
Remark |
01 | Foundation work | 100% completed. | |
02 | Super Structure work | 100% completed. | |
03 |
Block Work |
Basement=100%
G. F.=60% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100%, Roof= 100% |
|
04 |
Electrical Conducting work |
Basement=60%
G. F=50% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100%, Roof = 100% |
|
05 |
Door frame fitting work |
Basement=100%
G. F=100%
A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=100%, B5=100%, A6=100%, B6=100%, A7=100%, B7=100%, A8=100%, B8=100% |
|
06 |
Sanitary & plumbing line work |
Basement=20%
G. F=30%
A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=70%, B5=70%, A6=75%, B6=70%, A7=70%, B7=70%, A8=70%, B8=70%, |
|
07 |
In side Plastering work |
Basement=80%
G. F=20% A1= 100%, A2= 100%, A3= 100%, A4= 100%, A5=90%, B5=90%, A6=90%, B6=90%, A7=90%, B7=90%, A8=90%, B8=90%, |
|
08 |
Electrical cable wiring work |
Basement=60%
G, F=30% A1= 25%, A2= 25%, A3= 25%, A4= 25%, A5=60%, B5=60%, A6=60%, B6=60%, A7=0%, B7=0%, A8=0%, B8=0%, |
|
09 |
Wall Tiles work |
Basement=0% G, F=0%
A1= 80%, A2= 80%, A3= 80%, A4= 80%, A5=60%, B5=60%, A6=50%, B6=50%, A7=0%, B7=50%, A8=50%, B8=10%, |
|
10 |
Common sanitary & Plumbing line work |
Basement=20%
G, F=30% A1= 80%, A2= 80%, A3= 80%, A4= 80%, A5=60%, B5=60%, A6=60%, B6=60%, A7=60%, B7=60%, A8=60%, B8=60%, |
|
11 | Outside plastering work | 95 % Completed | |
12 |
Floor tiles/Marble work |
Basement=0%
G, F=0% A1= 90%, A2= 90%, A3= 90%, A4= 90%, A5=80%, B5=50%, A6=80%, B6=80%, A7=80%, B7=80%, A8=80%, B8=80%, |
|
13 | L.C.C work | 15% Completed | |
14 | Grill & Railing work | 90 % Completed | |
15 | Inside paint & Polishing work | 45 % Completed | |
16 | Switch -Socket fitting work | 5 % Completed | |
17 | Outside paint work | ||
18 | Door shutter work | 15 % Completed | |
19 | Aluminum work | 30 % Completeds | |
20 | Tiles Pointing work & Marble finishing work | ||
21 | Commode – Basin fitting work and C.P fittings work | 10 % Completed | |
22 | Lift/Generator /Substation /Solar work | 75% Completed | |
23 | Boundary wall /Ground floor development work | 75% Completed | |
24 | Roof top finishing work | 80% Completed | |
25 | Roof top Gardening work G.F Garden work | 35% Completed |
16604