Completion Date
February 2026
Status Updated
October, 2024
| SL. No | Name of the work | Progress details |
| 01 | Foundation work | 100 % |
| 02 | Super Structure work | 100% |
| 03 | Block Work | A-2= 90%, A-3= 90%, A-4=90%, A-5=90%, A-6= 90%
B-2=90%, B-3 =90%, B-4=90%, B-5= 40%,B-5= 90%, B-6= 40% C-2=90%, C-3 =90% , C-4= 90%, C-5=40%, C-6=70%, C-7= 70% |
| 04 | Electrical conducting work | Over all 40% |
| 05 | Door frame fitting work | A-2= 90%, B-2=90%, C-2=90%, A-3= 90%, B-3=90%, C-3=90%, A-4= 90%, B-4=90%, C-4=90%, A-5= 90%, B-5=90%, C-5=90%, |
| 06 | Sanitary & plumbing line work | N/A |
| 07 | In side Plastering work | Ceiling plaster on going (80%) |
| 08 | Electrical cable wiring work | N/A |
| 09 | Wall tiles work | N/A |
| 10 | Common sanitary & Plumbing line work | N/A |
| 11 | Outside plastering work | N/A |
| 12 | Floor tiles/Marble work | N/A |
| 13 | L.C.C work | N/A |
| 14 | Grill & Railing work | N/A |
| 15 | Inside paint & Polishing work | N/A |
| 16 | Switch -Socket fitting work | N/A |
| 17 | Outside paint work | N/A |
| 18 | Door shutter work | N/A |
| 19 | Aluminum work | N/A |
| 20 | Tiles Pointing work & Marble finishing work | N/A |
| 21 | Commode – Basin fitting work and C.P fittings work | N/A |
| 22 | Lift/Generator /Substation /Solar work | N/A |
| 23 | Boundary wall /Ground floor development work | N/A |
| 24 | Roof top finishing work | N/A |
| 25 | Roof top Gardening work G.F Garden work | N/A |