Completion Date
March 2025
Status Updated
October, 2024
SL. No | Name of the work | Progress details |
Foundation work | 100% Completed | |
Super Structure work | 100% completed | |
Block work | All flat 100% Complete, Common area 85% Complete. | |
Electrical conduit work | All flat 100% Complete, Common area 85% Complete | |
Door frame fitting work | All flat 100% Complete, Common area 90% Complete | |
Sanitary & plumbing line work | Internal Sanitary & Plumbing work all flat 100% Complete, Vertical line work 90 %Complete | |
In side Plastering work | All flat 100% Complete, Common area 85% Complete | |
Electrical cable wiring work | All flat 100% Complete, Common area 70% Complete | |
Wall tiles work | All flat 99% Completed | |
Common sanitary & Plumbing line work | 40% completed | |
Outside plastering work | 98% completed | |
Floor tiles/Marble work | 100% Completed | |
L.C.C work | 100% Completed | |
Grill & Railing work | 90% Completed | |
Inside paint & Polishing work | 75% Completed | |
Switch -Socket fitting work | 55% Completed | |
Outside paint work | 50% Completed | |
Door shutter work | 60% Completed | |
Aluminum/Glazing work | 60% Completed | |
Tiles Pointing work & Marble finishing work | 45% Completed | |
Commode – Basin fitting work and C.P fittings work | 35% Completed | |
Lift/Generator /Substation /Solar work | 40% Completed | |
Boundary wall /Ground floor development work | 45% Completed | |
Roof top finishing work | 40% Completed | |
Roof top Gardening work | 10% Completed |