Royal Pines

Mirpur, Dhaka

Completion Date

March 2025

Status Updated

October, 2024

SL. No Name of the work Progress details
  Foundation work 100% Completed
  Super Structure work 100% completed
  Block work All flat 100% Complete, Common area 85% Complete.
  Electrical conduit work All flat 100% Complete, Common area 85% Complete
  Door frame fitting work All flat 100% Complete, Common area 90% Complete
  Sanitary & plumbing line work Internal Sanitary & Plumbing work all flat 100% Complete, Vertical line work 90 %Complete
  In side Plastering work All flat 100% Complete, Common area 85% Complete
  Electrical cable wiring work All flat 100% Complete, Common area 70% Complete
  Wall tiles work All flat 99% Completed
  Common sanitary & Plumbing line work 40% completed
  Outside plastering work 98% completed
  Floor tiles/Marble work 100% Completed
  L.C.C work 100% Completed
  Grill & Railing work 90% Completed
  Inside paint & Polishing work 75% Completed
  Switch -Socket fitting work 55% Completed
  Outside paint work 50% Completed
  Door shutter work 60% Completed
  Aluminum/Glazing work 60% Completed
  Tiles Pointing work & Marble finishing work 45% Completed
  Commode – Basin fitting work and C.P fittings work 35% Completed
  Lift/Generator /Substation /Solar work 40% Completed
  Boundary wall /Ground floor development work 45% Completed
  Roof top finishing work 40% Completed
  Roof top Gardening work 10% Completed

 