Completion Date
January 2025
Status Updated
October, 2024
| SL. No | Name of the work | Location | Progress details | Remarks |
| 01 | Foundation work | 100% completed. | ||
| 02 | Super Structure work | 100% | ||
| 03 | Block Work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
| 04 | Electrical conduiting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 05 | Door frame fitting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete |
|
| 06 | Sanitary & plumbing line work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9
|
98% Complete
98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete 98% Complete |
|
| 07 | In side Plastering work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 08 | Electrical cable wiring work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9
|
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 09 | Wall tiles work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 10 | Common sanitary & Plumbing line work | 90%Complete
|
||
| 11 | Outside plastering work | 100% Complete | ||
| 12 | Floor tiles/Marble work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100% Complete
100% Complete 100%Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete 100% Complete
|
|
| 13 | L.C.C work |
100%
|
||
| 14 | Grill & Railing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100%
100% 100% 100% 100% 100% 100% 100% 100% |
|
| 15 | Inside paint & Polishing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
80%
80% 80% 80% 80% 80% 80% 80% 80%
|
|
| 16 | Switch -Socket fitting work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
0%
100% 100% 100% 100% 100% 100% 100% 100%
|
|
| 17 | Outside paint work | 40% | ||
| 18 | Door shutter work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
100%
100% 100% 100% 100% 100% 100% 100% 100%
|
|
| 19 | Aluminum work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
85%
85% 85% 85% 85% 85% 85% 85% 85%
|
|
| 20 | Tiles Pointing work & Marble finishing work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
0%
0% 0% 0% 0% 0% 0% 0% 0%
|
|
| 21 | Commode – Basin fitting work and C.P fittings work | Apartment =A1
Apartment =A2 Apartment =A3 Apartment =A4 Apartment =A5 Apartment =A6 Apartment =A7 Apartment =A8 Apartment =A9 |
0%
0% 0% 0% 0% 0% 0% 0% 0%
|
|
| 22 | Lift/Generator /Substation /Solar work | 85% | ||
| 23 | Boundary wall /Ground floor development work | 98%Complete | ||
| 24 | Roof top finishing work | 98%Complete | ||
| 25 | Roof top Gardening work G.F Garden work | 70% |