Completion Date
October 2026
Status Updated
October, 2024
| SL. No | Name of the work | Progress details |
| Foundation work | 100% Completed | |
| Super Structure work | Tower-1: Ground floor slab 100%,1st floor slab 100%,2nd floor slab 100%,3rd floor slab 100%,4th floor slab 100%.
5th floor 100%, 5th floor column 100%. 6th floor slab 100%, 7th floor slab 100%. 8th floor column 100%,9th floor slab 100%.
Tower-2: 1st floor slab 100%,2nd floor slab 100%, 3rd floor slab 100% ,4th floor slab 100%. 5th floor slab 100%. 6th floor slab 100%, 6th floor column 100%,7th floor slab 100%, 8th floor 100%
|
|
| Block work | Tower-1: Ground floor Substation room, Stair wall 90%. 1st floor 70%, 2nd floor 90%, 3rd floor 90%, 4th floor 70%,5th floor 80%, 6th 80%,7th floor 60%
Tower-2: 1st floor 80%, 2nd floor 80%,3rd floor 80%, 4th floor 80%, 5th floor 60%, |
|
| Electrical conduit work | Tower-1: 1st floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%,4th floor slab conduiting 100%,5th floor slab conduiting 100%. 6th floor slab 100%,7th floor 100%, 8th floor slab 100%, 9th floor slab 100%
Tower-2:1st floor floor slab conduiting100%, 2nd floor slab conduiting 100%, 3rd floor slab conduiting 100%. 4th floor slab 100%,5th floor 100%,6th floor slab 100%,7th floor slab 100%. 8th floor 80%
|
|
| Door frame fitting work | 60 | |
| Sanitary & plumbing line work | N/A | |
| In side Plastering work | Tower-1 Basement ceiling Plaster 100%,
Ground floor ceiling Plaster 90%, 2nd floor celling 100%, 4th floor 100%,5th floor 100%, 6th floor slab 100%,7th floor 100% , 8th floor slab 100%
Tower-2 1st floor celling 100%,2nd floor ceiling 100%, 3rd floor 100%, 4th floor 100%, 5th floor 100%,6th floor 100% |
|
| Electrical cable wiring work | Basement 40%, Ground floor 50%. | |
| Wall tiles work | N/A | |
| Common sanitary & Plumbing line work | N/A | |
| Outside plastering work | N/A | |
| Floor tiles/Marble work | N/A | |
| L.C.C work | N/A | |
| Grill & Railing work | N/A | |
| Inside paint & Polishing work | N/A | |
| Switch -Socket fitting work | N/A | |
| Outside paint work | N/A | |
| Door shutter work | N/A | |
| Aluminum/Glazing work | N/A | |
| Tiles Pointing work & Marble finishing work | N/A | |
| Commode – Basin fitting work and C.P fittings work | N/A | |
| Lift/Generator /Substation /Solar work | N/A | |
| Boundary wall /Ground floor development work | N/A | |
| Roof top finishing work | N/A | |
| Roof top Gardening work | N/A |
16604