Welcome Home

Mirpur, Dhaka

Completion Date

November 2026

Status Updated

October, 2024

Name of the work Progress details
Foundation work 99% Completed
Super Structure work 70% completed
Block work A1=100%, A2=100%, A3=90%, A4=90%, A5=80%,  A6=80%, A7=60%, B1=100%, B2=100%, B3=90%, B4=90%, B5=90%, B6=70%, B7=50%,  C1=100%, C2=90%, C3=90%, C4=80%, C5=80%, C6=80%,  C7=5%,  D1=100%, D2=100%, D3=100%, D4=90%, D5=90%, D6=70%, D7=70%,   E1=90%, E2=100%, E3=100%, E4=90%, E5=80%, E6=70%, E7=70%,  F1=90%, F2=100%, F3=90%, F4=80%,  F5=90%, F6=80%, F7=70%, G1=90%, G2= 90% G3=80%,  G6=70%, G7=70%,  H1= 90%, H2=90%, H3=90%, H4=60%, H5=70%,   H6=10%,  H7=20%,  I1=95%,  I2=90%, I3=20%, I4=70%, I5=70%, I6=10%, I7=20%,  J1= 10%, J2=70%, J3=70%,  J4=50%,  K1=95% K2= 90%, K3=90%, K4=70% K5=70%, K6=70%, K7=60%,
  A1=100%, A2=100%, A3=80%, A4=80%, A5=70%, A6=70%, A7=50%, B1=100%, B2=100%, B3=80%, B4=80%, B5=80%, B6=60%, B7=40%,  C1=100%, C2=90%, C3=80%, C4=80%,  C5=80%, C6=80%,   D1=100%, D2=100%, D3=100%, D4=80%, D5=90%, D6=60%, D7=60%, E1=90%, E2=100%, E3=100%, E4=90%, E5=80%, E6=60%, E7=60%, F1=90%, F2=100%, F3=80%, F4=80%, F5=70%, F6=70%, F7=60%, G1=90%, G2=  90% G3=  80% G6=60%, G7=60%, H1= 90%, H2=90%, H3=90%, H4=50%,  H5=60%,   H6=00%,  H7=00%,  I1=95% I2=70%, I3=60%, I4=50%, I5=60%, J1= 10%, J2=60%, J3=60%, J4=40%,  K1=95%, K2= 80%, K3=70%, K4=70% , K5=50%, K6=50%, K7=50%,
Door frame fitting work A1=95%, B1=95%, C1=95%, A2=95%, B2=80%, H1=80%, I1=80%,
Sanitary & plumbing line work N/A
In side Plastering work Tower1&2, Basement Ceiling=95%

GF Ceiling= 95%, 1st Floor Ceiling= 95%, 2nd Floor Ceiling= 95% 3rd Floor Ceiling=95%, 4th Floor Ceiling=90%, 5th Floor Ceiling=90%, 6th Floor Ceiling=90%, 7th Floor Ceiling=90%, 8th Floor Ceiling=20%,

Inside Wall Plaster: 1st floor 50%

Electrical cable wiring work Basement= 90%, Ground Floor=60%
Wall tiles work N/A
Common sanitary & Plumbing line work N/A
Outside plastering work N/A
Floor tiles/Marble work N/A
L.C.C work N/A
Grill & Railing work N/A
Inside paint & Polishing work N/A
Switch -Socket fitting work N/A
Outside paint work N/A
Door shutter work N/A
Aluminum/Glazing work N/A
Tiles Pointing work & Marble finishing work N/A
Commode – Basin fitting work and C.P fittings work N/A
Lift/Generator /Substation /Solar work N/A
Boundary wall /Ground floor development work N/A
Roof top finishing work N/A
Roof top Gardening work N/A

 

16604